Moderators: richierich, ua900, PanAm_DC10, hOMSaR

 
User avatar
Mortyman
Topic Author
Posts: 6416
Joined: Sat Aug 12, 2006 8:26 pm

Norway is consdiering cancelling troublesome order ...

Sat Oct 28, 2017 1:45 am

The Norwegian Armed Forces considers the NH90 contract to be broken and "considering alternative solutions" after 11 years of delays in the NH90 helicopters. The Defense Staff now put down a working group to look at different alternatives. A cancellation is probably not excluded.

Norway agreed back in 2001 to buy 14 NH90 helicopters. The manufacturer, NHIndustries, was to supply eight helicopters to the Coast Guard and six to the Navy. According to the contract, the helicopters would be delivered in the summer of 2006. But they never were.. Today, more than 11 years after, only six helicopters are delivered to the Coast Guard. But these are not finished and certified editions. For example, they can not be used in bad weather. The frigates, for their part, have not yet one flight time with their helicopters.

Norway has continually accepted new delays, and still new assurances from the manufacturer that the helicopters are coming soon. But 11 years of delays show two things: The manufacturer's credibility is no longer what it was. And the Norwegian authorities have lacked a good exit strategy. Delays can not be rectified, but a decision on what will happen next can be on the stairs.

Sweden, who originally ordered the same helicopters, gave up already in spring 2011 (after "just" about five years with delays). It was after all to judge a good decision. The Swedes canceled the order and instead received new helicopters delivered from the competitor Sikorsky the following year, in 2012. Sikorsky spent 16 months delivering 15 factory new helicopters.

Total failure on all criteria


Norway has had a lot more patience. But now, the Armed Forces have has had enough. They consider the contract with the supplier as broken.

"We know that they are unable to deliver what the contract was due to," confirms the Navy information manager, Change Barane.

The background is obvious, but the Navy chooses to describe it in a somewhat technical way: The contract requires that the manufacturer not only deliver the helicopters themselves. It will also be delivered on different criteria such as the number of flight hours. In addition, maintenance work shall be measured against the number of flight hours to see how much maintenance is needed per flight time. Finally, the helicopters will deliver on operational requirements. For example, they should land on Coast Guard, have a certain range, equipment requirements, and so on.

The Armed Forces have previously stated that the operational requirements are not fulfilled - The Coast Guard Helicopters can not land on their vessels at the moment. It may be that the situation will be fine in three to five years, but it is uncertain. The frigate helicopters are not delivered and consequently do not meet any operational requirements.

The new now is that the contract is also broken in proportion to the number of flight hours that the helicopters can deliver.

Has set up a working group to consider

The Armed Forces have now set up a working group to assess different possibilities. Neither the Armed Forces nor the Ministry of Defense has answered in detail what the mandate the group has, but the following possibilities may be relevant:

• A cancellation of the contract
• Civil lawsuits against the manufacturer
• Demand for price reductions
• Requirements for changes to the helicopters


Partly translated from Norwegian

https://www.aldrimer.no/nh90-forsvaret- ... losninger/


The NH90 could have been a great helicopter and I think it's a shame that it's not working out, but I do hope at this poijnt that the Norwegian government come to their sences and get a different helicopter. They have been way to patient With the supplier.
• Ultimatum or absolute deadlines.
 
User avatar
SAS A340
Posts: 946
Joined: Fri Jul 28, 2000 5:59 am

Re: Norway is consdiering cancelling troublesome order ...

Sat Oct 28, 2017 4:48 am

Sweden didn´t cancelled the order of NH90, the order of UH60M "Black Hawk" was partly done due to NH90,s difficulty to be delivered on time, but we have both systems in Sweden today. Sweden also wanted a model with "high cabin" which meant that it pulled out even longer at the time of delivery

Timeline (NH90)

2001 draw FMV contract with NHI for delivery of 18 helicopters
2011 delivers the FMV for the first four Hkp 14 Basic TTT to the armed forces. Used for training
2013-14 delivers FMV five Hkp 14 D for international operations and the building of naval operational capabilities
2015 delivers FMV two Hkp 14 (D) and the first Hkp 14 F with sonar and tactical radar
2016 will FMV to deliver three more Hkp 14 (F)
2017 delivered the last Hkp 14 F to Försvasmakten
2017-20 14 D 13 Hkp will gradually be upgraded to E-version

Timeline (UH60M)

In the summer of 2010, the Government decided that a completely new helicopter system would be acquired.
After the evaluation of various alternative systems decided the FMV in early 2011 to begin final negotiations with the U.S. authorities on the purchase of 15 UH-60 m Black Hawk from Sikorsky Aircraft Corporation. Sweden acquires UH-60 m Black Hawk via an intergovernmental agreement with the United States, through a so called FMS case (Foreign Military Sales)
In november 2011, the United States handed the first helicopters to the FMV at Sikorsky's factory in Stratford, United States
In december 2011, were the first two helicopters are on site at FMV on the ore in Linköping
January 2012 was the formal handover to the Swedish armed forces

The rapid delivery of the UH60M was because it was an originaly a order for the United States but that it ceded them to Sweden instead if my memory doesen´t fail me ;)
 
User avatar
Dutchy
Posts: 13364
Joined: Sat Nov 03, 2007 1:25 am

Re: Norway is consdiering cancelling troublesome order ...

Sat Oct 28, 2017 7:13 am

Why is the NH90 such a failure in so many respects? Everyone who ordered it saw delays and cost increase. I think the Dutch still experiences some operational difficulties. Such a shame for such a beautiful machine.
 
ThePointblank
Posts: 4426
Joined: Sat Jan 17, 2009 11:39 pm

Re: Norway is consdiering cancelling troublesome order ...

Sat Oct 28, 2017 7:30 am

Dutchy wrote:
Why is the NH90 such a failure in so many respects? Everyone who ordered it saw delays and cost increase. I think the Dutch still experiences some operational difficulties. Such a shame for such a beautiful machine.

Easy: too many cooks in the kitchen spoil the broth. Notice that while there are supposed to be 2 major variants, each end user has their own sub-variant that invariably makes the specific version built for that user a unique product.
 
User avatar
Dutchy
Posts: 13364
Joined: Sat Nov 03, 2007 1:25 am

Re: Norway is consdiering cancelling troublesome order ...

Sat Oct 28, 2017 7:31 am

They never learn..................
 
ThePointblank
Posts: 4426
Joined: Sat Jan 17, 2009 11:39 pm

Re: Norway is consdiering cancelling troublesome order ...

Sat Oct 28, 2017 8:46 am

Dutchy wrote:
They never learn..................

I would also add 6 parallel production lines all producing the same aircraft for each major user... not exactly a best practice example for production efficiency...
 
User avatar
Dutchy
Posts: 13364
Joined: Sat Nov 03, 2007 1:25 am

Re: Norway is consdiering cancelling troublesome order ...

Sat Oct 28, 2017 10:47 am

Again, they never learn.......
 
tommy1808
Posts: 14915
Joined: Thu Nov 21, 2013 3:24 pm

Re: Norway is consdiering cancelling troublesome order ...

Sat Oct 28, 2017 2:53 pm

ThePointblank wrote:
Dutchy wrote:
They never learn..................

I would also add 6 parallel production lines all producing the same aircraft for each major user... not exactly a best practice example for production efficiency...


Actually that is what Airbus is doing and, looking at the market share, one could call that best practice. Of course someone would need to replicate the internal competition as well.
But you do need to build one model in one or two variants.

Best regards
Thomas
 
User avatar
Dutchy
Posts: 13364
Joined: Sat Nov 03, 2007 1:25 am

Re: Norway is consdiering cancelling troublesome order ...

Sat Oct 28, 2017 2:58 pm

500 vs 13.000 production run, that makes a difference. This is done for political reasons, not for economic ones.
 
VSMUT
Posts: 5496
Joined: Mon Aug 08, 2016 11:40 am

Re: Norway is consdiering cancelling troublesome order ...

Sat Oct 28, 2017 7:59 pm

Mortyman wrote:
The Norwegian Armed Forces considers the NH90 contract to be broken and "considering alternative solutions" after 11 years of delays in the NH90 helicopters. The Defense Staff now put down a working group to look at different alternatives. A cancellation is probably not excluded.


And yet, they just decided to order practically the same EH-101 variant Denmark has, a variant that is still causing major headaches over 10 years after they were delivered. Sounds more like incompetence on behalf of the Norwegian military if you ask me. It is also worth noting that the NH-90 hasn't had anywhere near as many problems in France and Italy among others.

ThePointblank wrote:
Dutchy wrote:
They never learn..................

I would also add 6 parallel production lines all producing the same aircraft for each major user... not exactly a best practice example for production efficiency...


That's pretty priceless coming from such an adamant JSF proponent as yourself. 3 assembly lines, and production spread out over as many states and countries as possible. Your criticism of the F-35 is noted.
 
bigjku
Posts: 1906
Joined: Sat Feb 17, 2007 10:51 pm

Re: Norway is consdiering cancelling troublesome order ...

Sat Oct 28, 2017 9:29 pm

The F-35 program is producing huge numbers of the most advanced combat fighter ever built. The NH-90 is making the equivalent of a truck.

Having difficulty with a highly ambitious fighter aircraft is annoying but understandable, see Eurofighter, Rafale, SU-57 and pretty much every fighter in the last 30 years. Making a hash of building a battlefield truck is stupid and unnecessary. All the money spent buys you very little new capability in that case over just buying things that exist. It will come and go and UH-60’s will still be rolling out and being improved.
 
User avatar
Mortyman
Topic Author
Posts: 6416
Joined: Sat Aug 12, 2006 8:26 pm

Re: Norway is consdiering cancelling troublesome order ...

Sat Oct 28, 2017 11:36 pm

VSMUT wrote:
Mortyman wrote:
The Norwegian Armed Forces considers the NH90 contract to be broken and "considering alternative solutions" after 11 years of delays in the NH90 helicopters. The Defense Staff now put down a working group to look at different alternatives. A cancellation is probably not excluded.


And yet, they just decided to order practically the same EH-101 variant Denmark has, a variant that is still causing major headaches over 10 years after they were delivered. Sounds more like incompetence on behalf of the Norwegian military if you ask me. It is also worth noting that the NH-90 hasn't had anywhere near as many problems in France and Italy among others.

ThePointblank wrote:
Dutchy wrote:
They never learn..................

I would also add 6 parallel production lines all producing the same aircraft for each major user... not exactly a best practice example for production efficiency...


That's pretty priceless coming from such an adamant JSF proponent as yourself. 3 assembly lines, and production spread out over as many states and countries as possible. Your criticism of the F-35 is noted.



It is the producer that are not able to deliver the promised Product to the promised time. It is now 11 years over due time ! Hardly incompetence on the Norwegian part, but the producer. Furthermore, Norway is not the only country that has had problems With the NH90. Don't know about France and Italy. They may have different criteria and different conditions. Fact of the matter is that the producer has not met it's promises and have gotten ample time to solve the probelms. Again 11 years over due !
 
ThePointblank
Posts: 4426
Joined: Sat Jan 17, 2009 11:39 pm

Re: Norway is consdiering cancelling troublesome order ...

Sun Oct 29, 2017 2:22 am

VSMUT wrote:

ThePointblank wrote:
Dutchy wrote:
They never learn..................

I would also add 6 parallel production lines all producing the same aircraft for each major user... not exactly a best practice example for production efficiency...


That's pretty priceless coming from such an adamant JSF proponent as yourself. 3 assembly lines, and production spread out over as many states and countries as possible. Your criticism of the F-35 is noted.

Yeah, 3 production lines that are producing the SAME exact aircraft for everyone, and you are knocking out thousands of them.

Compare that to 6 production lines producing multiple individual sub-variants for each customer. And you are only producing maybe a couple dozen of each sub-variant.

One makes a lot more sense than the other. Hint: it's not the one with 6 production lines.
 
User avatar
Dutchy
Posts: 13364
Joined: Sat Nov 03, 2007 1:25 am

Re: Norway is consdiering cancelling troublesome order ...

Sun Oct 29, 2017 6:52 am

Mortyman wrote:
VSMUT wrote:
Mortyman wrote:
The Norwegian Armed Forces considers the NH90 contract to be broken and "considering alternative solutions" after 11 years of delays in the NH90 helicopters. The Defense Staff now put down a working group to look at different alternatives. A cancellation is probably not excluded.


And yet, they just decided to order practically the same EH-101 variant Denmark has, a variant that is still causing major headaches over 10 years after they were delivered. Sounds more like incompetence on behalf of the Norwegian military if you ask me. It is also worth noting that the NH-90 hasn't had anywhere near as many problems in France and Italy among others.

ThePointblank wrote:
I would also add 6 parallel production lines all producing the same aircraft for each major user... not exactly a best practice example for production efficiency...


That's pretty priceless coming from such an adamant JSF proponent as yourself. 3 assembly lines, and production spread out over as many states and countries as possible. Your criticism of the F-35 is noted.



It is the producer that are not able to deliver the promised Product to the promised time. It is now 11 years over due time ! Hardly incompetence on the Norwegian part, but the producer. Furthermore, Norway is not the only country that has had problems With the NH90. Don't know about France and Italy. They may have different criteria and different conditions. Fact of the matter is that the producer has not met it's promises and have gotten ample time to solve the probelms. Again 11 years over due !


Why is it that the Norwegian examples haven't been delivered? Hundreds are flying and even the line in Finland is closing or is already closed. Something doesn't add up here. If it was that pressing, they could just have made 6 more examples in Finland.
 
User avatar
Mortyman
Topic Author
Posts: 6416
Joined: Sat Aug 12, 2006 8:26 pm

Re: Norway is consdiering cancelling troublesome order ...

Sun Oct 29, 2017 7:46 am

Dutchy wrote:
Mortyman wrote:
VSMUT wrote:

And yet, they just decided to order practically the same EH-101 variant Denmark has, a variant that is still causing major headaches over 10 years after they were delivered. Sounds more like incompetence on behalf of the Norwegian military if you ask me. It is also worth noting that the NH-90 hasn't had anywhere near as many problems in France and Italy among others.



That's pretty priceless coming from such an adamant JSF proponent as yourself. 3 assembly lines, and production spread out over as many states and countries as possible. Your criticism of the F-35 is noted.



It is the producer that are not able to deliver the promised Product to the promised time. It is now 11 years over due time ! Hardly incompetence on the Norwegian part, but the producer. Furthermore, Norway is not the only country that has had problems With the NH90. Don't know about France and Italy. They may have different criteria and different conditions. Fact of the matter is that the producer has not met it's promises and have gotten ample time to solve the probelms. Again 11 years over due !


Why is it that the Norwegian examples haven't been delivered? Hundreds are flying and even the line in Finland is closing or is already closed. Something doesn't add up here. If it was that pressing, they could just have made 6 more examples in Finland.



I beleave the Finnish has a different version. The army version. There are different problems with operating the helicopters at sea I think one of the problems is corrosion wich also the Netherlands navy has had a problem With. I Guess. Norway has ordered the Frigate and Coastguard Versions.

Furthermore, it's not like the Finnish hasn't had their share of problems also:

From Wikipedia:

In January 2015, it was reported that Finnish NH90s had been experiencing considerable reliability issues, at one time in 2014 fleet availability dipped to 19%, and some spare parts had up to seven months waiting time. By early 2015, the combined NH90s fleet had accumulated a total of 7,000 flight hours, and had an availability rate of 40%. On 18 June 2015, delivery of the final Finnish NH90 took place. In November 2015, the availability rate was reported as having surpassed 50 percent.



Please read the original post again.
 
User avatar
Dutchy
Posts: 13364
Joined: Sat Nov 03, 2007 1:25 am

Re: Norway is consdiering cancelling troublesome order ...

Sun Oct 29, 2017 8:09 am

Corrosion problems should have been solved, the Dutch have taken delivery again. There are other countries flying the Navy version as well. So again, what is so darn special about the Norwegian examples that they can't be produced and can't be delivered? We are missing something here and I don't know what. This can't be the whole story.
 
User avatar
Mortyman
Topic Author
Posts: 6416
Joined: Sat Aug 12, 2006 8:26 pm

Re: Norway is consdiering cancelling troublesome order ...

Sun Oct 29, 2017 9:01 am

Dutchy wrote:
Corrosion problems should have been solved, the Dutch have taken delivery again. There are other countries flying the Navy version as well. So again, what is so darn special about the Norwegian examples that they can't be produced and can't be delivered? We are missing something here and I don't know what. This can't be the whole story.




They apparently are not able to deliver the helicopters With the requirements that was agreed on:


The background is obvious, but the Navy chooses to describe it in a somewhat technical way: The contract requires that the manufacturer not only deliver the helicopters themselves. It will also be delivered on different criteria such as the number of flight hours. In addition, maintenance work shall be measured against the number of flight hours to see how much maintenance is needed per flight time. Finally, the helicopters will deliver on operational requirements. For example, they should land on Coast Guard, have a certain range, equipment requirements, and so on.

The Armed Forces have previously stated that the operational requirements are not fulfilled - The Coast Guard Helicopters can not land on their vessels at the moment. It may be that the situation will be fine in three to five years, but it is uncertain. The frigate helicopters are not delivered and consequently do not meet any operational requirements.



Image


Image


Image


Image


Image
 
User avatar
Dutchy
Posts: 13364
Joined: Sat Nov 03, 2007 1:25 am

Re: Norway is consdiering cancelling troublesome order ...

Sun Oct 29, 2017 11:02 am

The frigate helicopters are not delivered and consequently do not meet any operational requirements.


That is the whole point, sure operational requirements are met if they are not delivered. OMG I can imagine that. But the question is, why are they not delivered? Because other nations took delivery of the navy variant. What is so special about the Norwegian examples. Sure I do recognize that NH industry has done a lot of things wrong in the past and they are late to deliver, but this seems to be an issue with the Norwegian examples alone. And that makes it interesting, especially looking at the Norwegian side of things. This can't be pure a NH industry thing, otherwise, other nations would experience the same issues.
 
User avatar
Slug71
Posts: 1531
Joined: Wed Jan 04, 2017 6:08 am

Re: Norway is consdiering cancelling troublesome order ...

Sat Nov 11, 2017 11:32 pm

The troubles with the NH90 project is also just another shame. Such a good looking helo with a lot of potential. For the most part, it does seem to be getting over it's teething issues though.

Might be time to give it a little update. Would love to see it get a Fenestron.
 
ZaphodHarkonnen
Posts: 1479
Joined: Sun Jan 04, 2015 10:20 am

Re: Norway is consdiering cancelling troublesome order ...

Tue Nov 14, 2017 3:40 pm

It's weird seeing stories like this while at home the RNZAF seems to have had bugger all problems with their new NH-90s. I wonder what the differences are that have led to these problems.
 
Ozair
Posts: 5584
Joined: Mon Jan 31, 2005 8:38 am

Re: Norway is consdiering cancelling troublesome order ...

Tue Nov 14, 2017 8:40 pm

ZaphodHarkonnen wrote:
It's weird seeing stories like this while at home the RNZAF seems to have had bugger all problems with their new NH-90s. I wonder what the differences are that have led to these problems.

The same reason I think that NZ didn't have problems with the SeaSprites against what Australia treid to do. NZ typically takes the baseline variant and does not try to modify or enhance the platform

In Australian Service the MRH-90 has been a joke. It was another program that brought in way too much risk and many of the problems stem from two things, a lack of proper program oversight and requirements definition by the Australian Government procurement agency and the inability of the MRH-90 to be able to operate in the threat environments required.

The ANAO conducted an audit of the program in 2014 and identified the following,

5. During the audit, the MRH90 Program was dealing with a range of challenges related to immaturity in the MRH90 system design and the support system. The challenges include:
resolving MRH90 cabin and role equipment design issues so that operational test and evaluation validates the MRH90 aircraft’s ability to satisfy Operational Capability Milestones set by Army and Navy;
the continuing need to conduct a wide range of verification and validation activities on problematic or deficient aircraft systems;
increasing the reliability, maintainability and flying rate of effort of the MRH90 aircraft;
embedding revised sustainment arrangements directed toward improving the value for money of these arrangements;
establishing a revised Australian industry activities plan, including performance metrics;
funding and managing the extended concurrent operation of the Army S‑70A‑9 Black Hawk and MRH90 aircraft fleets; and
managing a Navy capability gap following the retirement of the RAN Sea King aircraft in December 2011.


The full audit can be found here.
https://www.anao.gov.au/work/performance-audit/multi-role-helicopter-program

The irony of the procurement is that the Australian Department of Defence recommended the S-70M but the Government overruled and directed that the MRH-90 be selected instead.
 
ZaphodHarkonnen
Posts: 1479
Joined: Sun Jan 04, 2015 10:20 am

Re: Norway is consdiering cancelling troublesome order ...

Wed Nov 15, 2017 10:17 am

Sounds like a similar issue I find with IT projects in my line of work. When purchasing a platform you can either adapt it to your processes or adapt your processes to it. Generally groups want to adapt the platform but its usually easier to adapt your processes. As much as it irritates people.
 
User avatar
Dutchy
Posts: 13364
Joined: Sat Nov 03, 2007 1:25 am

Re: Norway is consdiering cancelling troublesome order ...

Wed Nov 15, 2017 10:19 am

ZaphodHarkonnen wrote:
Sounds like a similar issue I find with IT projects in my line of work. When purchasing a platform you can either adapt it to your processes or adapt your processes to it. Generally groups want to adapt the platform but its usually easier to adapt your processes. As much as it irritates people.


:checkmark:

Although NH Industries didn't do everything quite right with this platform, but those things seem to be ironed out by now.
 
User avatar
Slug71
Posts: 1531
Joined: Wed Jan 04, 2017 6:08 am

Re: Norway is consdiering cancelling troublesome order ...

Thu Nov 16, 2017 4:57 pm

Hopefully this and the A400M has been a big learning curve and wake up call for all parties involved.
You would think that after 10 years in production and with technology and other improvements, that would allow most of the individual requests to become standard equipment by now. Other than structural changes that is, like the higher ceiling for one of the users. You'd think all users would want the higher ceiling though.
 
Ozair
Posts: 5584
Joined: Mon Jan 31, 2005 8:38 am

Re: Norway is consdiering cancelling troublesome order ...

Fri Jan 12, 2018 9:48 pm

The Belgians aren't having a lot of luck with their NH-90 fleet either.

https://www.msn.com/nl-be/nieuws/nationaal/grote-problemen-met-nieuwe-reddingshelikopters-defensie/ar-AAuAjZ3

The jist is the 3 first helicopters (RN01, 02 and 03) are suffering from radar malfunction issues (which have been resolved with RN04 with the installation of a more reliable radar) as well as other issues. RN04 will be out for a month due to maintenance, the other 3 are at airbus for retrofits and fixes, the first is due to return in the spring. repairs take 3 to 6 months each.

Delays means the 3 remaining Westland SeaKing Mk.48 helicopters (witch were due to retire at the end of 2018) will soldier on until at least March 2019.
 
GRIVely
Posts: 143
Joined: Wed Dec 13, 2006 5:46 am

Re: Norway is consdiering cancelling troublesome order ...

Sat Jan 13, 2018 4:11 pm

Interesting article in today’s Wall Street Journal about problems with the new German F-125 frigate. Over cost, too complex, software not reliable, failed sea trials, etc. The Journal opined the basic problem was insufficient project management experience with large scale military projects. The money quote is “There’s a whole generation of German engineers who haven’t worked on a major defense project. It’s not that they lost this skill; they never learned it.”
 
vr773
Posts: 128
Joined: Sun Oct 15, 2017 5:10 am

Re: Norway is consdiering cancelling troublesome order ...

Sun Jan 14, 2018 6:55 pm

GRIVely wrote:
Interesting article in today’s Wall Street Journal about problems with the new German F-125 frigate. Over cost, too complex, software not reliable, failed sea trials, etc. The Journal opined the basic problem was insufficient project management experience with large scale military projects. The money quote is “There’s a whole generation of German engineers who haven’t worked on a major defense project. It’s not that they lost this skill; they never learned it.”


I don't really understand what this has to do with Norway's NH90s. The German NH90s work well now although they can't really be compared to the NH90s that the Norwegians ordered. But neither can the F-125.

That whole WSJ article is weird using quotes from think tank guys that don't make much sense to me to be honest. And then they are used to back up the very broad point that 'Germans can't do engineering and project management anymore'. I wouldn't have expected this lack of logic from a journalist working for a respectable newspaper. The article also claims that Germany has increased its military budget in order to meet the NATO 2% goal. That's just not true.
 
Ozair
Posts: 5584
Joined: Mon Jan 31, 2005 8:38 am

Re: Norway is consdiering cancelling troublesome order ...

Tue Oct 30, 2018 5:02 am

The Norwegian Office of the Auditor General has released another report on the NH-90 and it isn't good. Essentailly they continue to point out the short comings of the platform, the company and the Norwegian Military in managing the contract.

The full report is available in Norwegian here,
https://www.riksrevisjonen.no/rapporter ... etNH90.pdf

A short translation is below,

The Acquisition of New Helicopters for the Navy Has Failed In Several Areas

The supplier of new helicopters to the Armed Forces Coast Guard and for the frigates has a great deal of responsibility for the delays, but the Ministry of Defense, Defense and Defense has not followed up the procurement well enough.

The delivery of the NH90 helicopters appears to be taking 14 years longer than agreed. "There have been shortcomings in the contract, poor planning and lack of coordination and governance for long periods," says Per-Kristian Foss, the auditor-general.

The Office of the Auditor General's investigation of the acquisition of maritime helicopters to the Armed Forces (NH90) (Document 3: 3 (2018-2019) was handed over to the Storting on 25 October.

The Storting's assumptions with the decisions of several propositions regarding the acquisition in the period 2000-2012 have not been met. This is also true for the 14 helicopters being delivered during 2008 and their operational capability. So far, eight helicopters have been delivered, six of which are in an interim version. The final delivery is expected to be in 2022, but there is still great uncertainty about delivery and phasing-in.

Those who have been delivered have so far provided few hours of flight, are significantly less accessible than planned, and have had very limited operating activities. In 2017, only one helicopter was available - the rest were waiting for spare parts and maintenance. Maintenance needs have been found to be about 15 times greater than expected for final version. Operating costs appear to be very high.

It was assumed that a helicopter should be chosen with known technology and proven operational reliability. The contract, concluded in 2001, was owned by four companies in four countries, the NATO Helicopter Industries (NHI), without production experience and with a new, untested helicopter.

"NHI obviously has a lot of responsibility for delays. At the same time, important prerequisites for the acquisition have not been followed up well enough on the Norwegian side. The Ministry of Defense and the Armed Forces did not go into the basis for choosing NH90 more seriously, and did not take the risk seriously," said Foss.

The contract was not sufficiently quality-assured and has been shown to have too low a daily penalty to avoid delays, and a low maintenance guarantee. This has given the supplier weak incentives to comply with delivery obligations. The contract has also not ensured stable supply of spare parts.

"In the Armed Forces, neither the planning, the staffing nor the coordination of the parties involved has been good enough," says Foss. There have been no basic plans for the maintenance, supply and operation of the equipment. A draft plan for material was only available in July 2017 and was recently approved.

The need for coordination of many actors in a highly complex and comprehensive process has been underestimated.

"Weak planning of such a large project with so many players, partial deliveries and the great need for coordination has been an important reason for the weak progress. Insufficient staffing in both maintenance, spare parts and procurement has also contributed to the delays, Foss notes.

The NH90 project has lacked one owner, standing above all others, to take responsibility for effective coordination and decision-making. The Ministry of Defense has been distant and unclear as project owners, and has not had enough management to capture the challenges, so measures were not taken on time, the OAG points out.

"The department's late involvement is serious in our opinion, especially given the economic size and the major operational consequences for our ships," says Foss.

The Ministry of Defense has also given the Storting little information, the OAG considers.

"This applies, among other things, to the fact that the conditions of the Armed Forces and Defense Matériels, not just the supplier, have contributed to the delays; that it has not been informed of the very low number of flight lessons that have been possible with the helicopters, information about the phase-in on the vessels, and little about the serious consequences for the coast guards' ability to carry out their tasks, "says Foss.


Response from the Norwegian Ministry of Defence.

Using the Auditor-General’s Recommendations to Improve

The Office of the Auditor General has examined the procurement and phasing-in of the NH90 helicopter to the Armed Forces. "I am familiar with the issues, largely agree with the production, and we will follow up the recommendations," said Frank Bakke-Jensen, Defense Minister.

“The report of the Office of the Auditor General is useful. It provides a thorough review of the current issues of the NH90 project related to the procurement under several governments going back to 2001,” says the Minister of Defense.

The report of the Office of the Auditor General indicates that the Storting's decision and prerequisites for the acquisition of NH90 were not met. According to the original contract, the Armed Forces should have received 14 NH90 by 2008. The status today is that the Armed Forces have received eight machines: six in an interim version and two in the final configuration.

The supplier's shortcomings and delays are identified as significant causes of the delays, but both the Office of the Auditor General and the Minister for Defense agree on the risk that the purchase was not sufficiently considered when the decision to choose NH90 was taken.

The Office of the Auditor General's investigation shows that phasing-in and commissioning of the NH90 has been challenging. The Defense Minister says that these are matters that are subject to specific follow-up for the NH90 procurement and that both the Armed Forces and Defense Matériel have established closer cooperation through the establishment of a joint program board for the NH90.

"NH90 was chosen in 2001, and part of the challenges the OAG observes are much more taken into consideration in today's routines for project planning and implementation. We have learned the NH90 acquisition and the experience is being used in the sector to learn and to further develop the materials investment methods, "said the Minister of Defense.

Information to the Storting

The Office of the Auditor General points out that the information to the Storting could be better.

"We have provided detailed information about NH90's operational capability to the Storting through established channels. Also, budget proposals to the Storting have for several years informed about the NH90. In Prop 1 S (2018-2019) I have also expanded the NH90 project deal," said the Minister of Defense.

Maintenance requirement

The Defense Minister shares the OAG's concern regarding NH90's maintenance needs. However, it is too early to conclude what the load is, or whether it is possible to correct claims against the supplier in this context. It is only when NH90 in the final version has been put through an operating period in Norway will it be possible to know how much maintenance will be needed.

“The Office of the Auditor General points out that the NH90 would originally be a unit helicopter and thus reduce operating costs by using the same helicopter type in many functions. But already in 2007 it became clear that the NH90 would not replace Sea King as a rescue helicopter. In addition, the plan was also that cooperation with other nations would bring savings, but it has turned out that the nations have so different needs and requirements that the cooperation was not as extensive as hopes," said Defense Minister Bakke-Jensen.

Auditor-General's recommendations
The OAG's recommendations include ensuring that basic assumptions are clearly defined and taken care of throughout the procurement process, including in quality assurance of the contract. Assessing measures that ensure that plans are made for phasing in material on time, especially when many units and these are involved depend on each other to achieve effective phasing-in. Such a practice would improve substantial procurement, ensuring clear division of responsibilities and clear governance and authority relationships between the Ministry of Defense, Defense Matériel, Defense Staff and the relevant manufacturers.

“These are recommendations that we will listen to and include in our efforts to further develop framework, methods and processes for investment activities. Several steps have already been taken since the NH90 acquisition was initiated, and these largely respect the recommendations of the Office of the Auditor General.

“One step I would especially like to draw is the creation of Defense Materials in 2016 as a separate agency under the Ministry of Defense to strengthen strategic management of material investment and material management in the defense sector," said the Minister of Defense.

NH90 is customized for Norwegian requirements and is tailored to the needs of the Navy. There is no other helicopter on the market today that will provide equivalent capacity. Assessments have been made on several occasions of the possibility of terminating the NH90 contract, most recently after the Storting requested a review of the contract in 2017. Following overall assessments, it was concluded that continuing the NH90 procurement is the best way to meet the Armed Forces needs for maritime helicopters.

"It is possible to cover Defense's needs for flight hours, but it will cost significantly more than expected. However, I have stated that both frigates and coastguards will have the number of flight hours with the NH90 as we determined in the last long-term plan. The need for more money and the Armed Forces' need for flight hours beyond today's ambition will be addressed in the next long-term plan, and we are working on measures to reduce operating costs," said the Minister of Defense.

http://www.defense-aerospace.com/articl ... ition.html
 
User avatar
Kiwirob
Posts: 14853
Joined: Mon Jun 13, 2005 2:16 pm

Re: Norway is consdiering cancelling troublesome order ...

Tue Oct 30, 2018 7:40 am

Ozair wrote:
ZaphodHarkonnen wrote:
It's weird seeing stories like this while at home the RNZAF seems to have had bugger all problems with their new NH-90s. I wonder what the differences are that have led to these problems.

The same reason I think that NZ didn't have problems with the SeaSprites against what Australia treid to do. NZ typically takes the baseline variant and does not try to modify or enhance the platform

In Australian Service the MRH-90 has been a joke. It was another program that brought in way too much risk and many of the problems stem from two things, a lack of proper program oversight and requirements definition by the Australian Government procurement agency and the inability of the MRH-90 to be able to operate in the threat environments required.



This makes no sense because NZ ordered the same variant as Australia. So what has Australia done wrong which NZ didn't?

For ease of manufacture and logistics, New Zealand deliberately chose their NH90 configuration to be nearly identical to the larger Australian fleet
 
Ozair
Posts: 5584
Joined: Mon Jan 31, 2005 8:38 am

Re: Norway is consdiering cancelling troublesome order ...

Tue Oct 30, 2018 9:32 am

Kiwirob wrote:

This makes no sense because NZ ordered the same variant as Australia. So what has Australia done wrong which NZ didn't?

For ease of manufacture and logistics, New Zealand deliberately chose their NH90 configuration to be nearly identical to the larger Australian fleet

NZ has had its own NH-90 issues but the important thing to note is the difference between the two contracts and frankly the intent of the aircraft in the respective nations militaries. Australia wrote a difficult set of requirements for the aircraft to fulfil, requirements that it hasn't been able to meet. Australia was seeking a battlefield helicopter that could survive in essentially a high threat environment and the MRH-90 as delivered was not that aircraft. The ANAO report I linked to earlier is very clear on the issues and what caused them (including failures from Government, military and contractor).

Even in NZ service though the aircraft has struggled to fulfil the promises made, for example being significantly more costly to operate than advertised. NZ's issues also stem from not acquiring enough aircraft and that has created problems with their operation and deployment outside of NZ.
 
User avatar
Aesma
Posts: 16887
Joined: Sat Nov 14, 2009 6:14 am

Re: Norway is consdiering cancelling troublesome order ...

Tue Oct 30, 2018 9:50 am

So what is preventing the NH90 from landing on the Norwegian frigates ? Do they have a smaller deck than other frigates or something like that ? Or do the Norwegian want it to land in bad visibility, bad weather etc., something more difficult to achieve that what other navies ask ?

I know nothing about the new German frigate but if you look at a country that has continuously had many gigantic military programs running together since the 40s, aka the USA, they very often have many problems not dissimilar to the ones described for the Germans...
 
User avatar
Kiwirob
Posts: 14853
Joined: Mon Jun 13, 2005 2:16 pm

Re: Norway is consdiering cancelling troublesome order ...

Tue Oct 30, 2018 11:34 am

If this article is correct it appears NZ has the highest availability of all the NH90 operators.

http://apdr.realviewtechnologies.com/#folio=38
 
User avatar
keesje
Posts: 15156
Joined: Thu Apr 12, 2001 2:08 am

Re: Norway is consdiering cancelling troublesome order ...

Wed Oct 31, 2018 8:28 am

I'm trying to get support for a dedicated helicopter platform. If we concentrate helicopter VTOL topic here we can have more indept discussions and attract more knowledgeable participants. Helicopters / VTOL is IMO an exciting, dynamic and broad segment of aviation that deserves this, more than e.g. a new "political forum" (?!) that's now being worked on as we speak.

Also topics like this (RIP) could be discussed and concentrated here. I worked on the NH-90 and have opinions to share.

:arrow: Please take a few second to post a few words of support for this additional forum. Thnx!

https://www.airliners.net/forum/viewtopic.php?p=20823963#p20823963
 
ThePointblank
Posts: 4426
Joined: Sat Jan 17, 2009 11:39 pm

Re: Norway is consdiering cancelling troublesome order ...

Wed Oct 31, 2018 9:22 am

Aesma wrote:
So what is preventing the NH90 from landing on the Norwegian frigates ? Do they have a smaller deck than other frigates or something like that ? Or do the Norwegian want it to land in bad visibility, bad weather etc., something more difficult to achieve that what other navies ask ?

I know nothing about the new German frigate but if you look at a country that has continuously had many gigantic military programs running together since the 40s, aka the USA, they very often have many problems not dissimilar to the ones described for the Germans...


Probably a lack of certification that is originating from a lack of flight hours available to certify that the NH90 is fit for use on the Norwegian frigates. If the Norwegians are experiencing reliability and availability problems, this could cause the shipboard compatibility testing to get pushed out until there's enough flight hours available to do the testing.

You need to accumulate a certain amount of hours, under a variety of conditions in order to certify that the type is safe to operate from a ship. That includes determining handling characteristics, and developing CONOPS in order to effectively and safely operate the helicopter.
 
User avatar
Mortyman
Topic Author
Posts: 6416
Joined: Sat Aug 12, 2006 8:26 pm

Re: Norway is consdiering cancelling troublesome order ...

Sun Nov 04, 2018 11:34 am

These helicopters were supposed to have been delivered 14 years ago, but so far only 8 is operational, 6 of wich are in testing mode only. The maintenance cost is apparently 15 times higher than it was supposed to be . It has become a huge scandal in Norway. In 2017 only one of the helicopters were operational. The helicopters are not getting the flight hours they are supposed to have.
 
mxaxai
Posts: 3926
Joined: Sat Jun 18, 2016 7:29 am

Re: Norway is consdiering cancelling troublesome order ...

Fri Nov 09, 2018 5:49 pm

ThePointblank wrote:
Aesma wrote:
So what is preventing the NH90 from landing on the Norwegian frigates ? Do they have a smaller deck than other frigates or something like that ? Or do the Norwegian want it to land in bad visibility, bad weather etc., something more difficult to achieve that what other navies ask ?

I know nothing about the new German frigate but if you look at a country that has continuously had many gigantic military programs running together since the 40s, aka the USA, they very often have many problems not dissimilar to the ones described for the Germans...


Probably a lack of certification that is originating from a lack of flight hours available to certify that the NH90 is fit for use on the Norwegian frigates. If the Norwegians are experiencing reliability and availability problems, this could cause the shipboard compatibility testing to get pushed out until there's enough flight hours available to do the testing.

You need to accumulate a certain amount of hours, under a variety of conditions in order to certify that the type is safe to operate from a ship. That includes determining handling characteristics, and developing CONOPS in order to effectively and safely operate the helicopter.

It seems that the Norwegian Navy not only has few helicopters for their frigates, but is also (temporarily?) down one frigate. Not sure if it's salvageable. For now, 4 frigates remain in service.
https://www.dailymail.co.uk/news/articl ... ntrol.html

While not good for the ship-based role, this might allow more of the small NH-90 fleet to be used in its other roles.
 
User avatar
Kiwirob
Posts: 14853
Joined: Mon Jun 13, 2005 2:16 pm

Re: Norway is consdiering cancelling troublesome order ...

Fri Nov 09, 2018 7:33 pm

4 frigates do not remain in service, only 3 do, the 4th Otto Sverdrup is basically a parts hulk.
 
User avatar
Mortyman
Topic Author
Posts: 6416
Joined: Sat Aug 12, 2006 8:26 pm

Re: Norway is consdiering cancelling troublesome order ...

Fri Nov 09, 2018 9:05 pm

Kiwirob wrote:
4 frigates do not remain in service, only 3 do, the 4th Otto Sverdrup is basically a parts hulk.



No it's not
 
User avatar
Kiwirob
Posts: 14853
Joined: Mon Jun 13, 2005 2:16 pm

Re: Norway is consdiering cancelling troublesome order ...

Sat Nov 10, 2018 5:27 am

Mortyman wrote:
Kiwirob wrote:
4 frigates do not remain in service, only 3 do, the 4th Otto Sverdrup is basically a parts hulk.



No it's not


According to my neighbour who is in the Navy it is.
 
User avatar
Kiwirob
Posts: 14853
Joined: Mon Jun 13, 2005 2:16 pm

Re: Norway is consdiering cancelling troublesome order ...

Sat Nov 10, 2018 6:45 am

I think she's going to head for the scrappers.

Image
 
User avatar
Mortyman
Topic Author
Posts: 6416
Joined: Sat Aug 12, 2006 8:26 pm

Re: Norway is consdiering cancelling troublesome order ...

Sat Nov 10, 2018 1:44 pm

Kiwirob wrote:
Mortyman wrote:
Kiwirob wrote:
4 frigates do not remain in service, only 3 do, the 4th Otto Sverdrup is basically a parts hulk.



No it's not


According to my neighbour who is in the Navy it is.



Hardly:

2 days ago:

TRIDENT JUNCTURE 2018 - American Vice Admiral Lisa Franchetti Visits HNoMS Otto Sverdrup During Trident Juncture:

https://www.youtube.com/watch?v=v1DsmPnzNPM
 
P1aneMad
Posts: 467
Joined: Thu Jan 26, 2017 2:05 pm

Re: Norway is consdiering cancelling troublesome order ...

Sat Nov 10, 2018 4:48 pm

The frigate was hit on its starboard side, if I am not hugely mistaken in maritime law you have to give right of way to the vessel coming from your right. So barring some other factors this accident was the fault of the frigate's crew manning the bridge at the time and not the oil tanker's.
Does anyone have any more info?
 
User avatar
Kiwirob
Posts: 14853
Joined: Mon Jun 13, 2005 2:16 pm

Re: Norway is consdiering cancelling troublesome order ...

Sat Nov 10, 2018 5:53 pm

Mortyman wrote:
Kiwirob wrote:
Mortyman wrote:


No it's not


According to my neighbour who is in the Navy it is.



Hardly:

2 days ago:

TRIDENT JUNCTURE 2018 - American Vice Admiral Lisa Franchetti Visits HNoMS Otto Sverdrup During Trident Juncture:

https://www.youtube.com/watch?v=v1DsmPnzNPM


Well then it’s one of the other three. I thought it was Otto.
 
User avatar
Mortyman
Topic Author
Posts: 6416
Joined: Sat Aug 12, 2006 8:26 pm

Re: Norway is consdiering cancelling troublesome order ...

Sat Nov 10, 2018 10:38 pm

P1aneMad wrote:
The frigate was hit on its starboard side, if I am not hugely mistaken in maritime law you have to give right of way to the vessel coming from your right. So barring some other factors this accident was the fault of the frigate's crew manning the bridge at the time and not the oil tanker's.
Does anyone have any more info?


The question is if the frigate had enough space to go to the "correct" side.
 
Ozair
Posts: 5584
Joined: Mon Jan 31, 2005 8:38 am

Re: Norway is consdiering cancelling troublesome order ...

Sun Nov 11, 2018 3:27 am

Mortyman wrote:
P1aneMad wrote:
The frigate was hit on its starboard side, if I am not hugely mistaken in maritime law you have to give right of way to the vessel coming from your right. So barring some other factors this accident was the fault of the frigate's crew manning the bridge at the time and not the oil tanker's.
Does anyone have any more info?


The question is if the frigate had enough space to go to the "correct" side.

According to Defence news it was docked at the time so clearly not enough room to avoid a collision...

https://www.defensenews.com/naval/2018/ ... -exercise/
 
P1aneMad
Posts: 467
Joined: Thu Jan 26, 2017 2:05 pm

Re: Norway is consdiering cancelling troublesome order ...

Sun Nov 11, 2018 9:19 am

Ozair wrote:
Mortyman wrote:
P1aneMad wrote:
The frigate was hit on its starboard side, if I am not hugely mistaken in maritime law you have to give right of way to the vessel coming from your right. So barring some other factors this accident was the fault of the frigate's crew manning the bridge at the time and not the oil tanker's.
Does anyone have any more info?


The question is if the frigate had enough space to go to the "correct" side.

According to Defence news it was docked at the time so clearly not enough room to avoid a collision...

https://www.defensenews.com/naval/2018/ ... -exercise/

So the frigate was docked and the collision took place inside a port? Something doesn't add up.
 
mxaxai
Posts: 3926
Joined: Sat Jun 18, 2016 7:29 am

Re: Norway is consdiering cancelling troublesome order ...

Sun Nov 11, 2018 9:33 am

P1aneMad wrote:
Ozair wrote:
Mortyman wrote:

The question is if the frigate had enough space to go to the "correct" side.

According to Defence news it was docked at the time so clearly not enough room to avoid a collision...

https://www.defensenews.com/naval/2018/ ... -exercise/

So the frigate was docked and the collision took place inside a port? Something doesn't add up.

According to the other article by defence news it was in a (narrow?) strait:

Local media reported that the Maltese-flagged tanker Sola TS identified Ingstad and tried to avoid the disaster. The reports also revealed details that show that Ingstad did not have a firm grasp of the surface picture it was sailing into.

The disaster developed quickly, with Ingstad transiting the channel inbound at 17 knots and Sola TS traveling outbound at 7 knots.

Sola TS raised the Ingstad multiple times and was discussing the emerging danger with shore-based Central Station, according to the Norwegian paper Verdens Gang. The responses from Ingstad appear confused, at one point saying that if they altered the course it would take them too close to the shoals, which prompted Sola TS to respond that they had to do something or a collision would be unavoidable.


Also:
Contributing to the confusion, the Ingstad appears to have been transiting with its Automatic Identification System switched off. That seems to have delayed recognition by central control and the other ships in the area that Ingstad was inbound and heading into danger, the account in VG seems to indicate.


https://www.defensenews.com/naval/2018/ ... t-we-know/
 
User avatar
Kiwirob
Posts: 14853
Joined: Mon Jun 13, 2005 2:16 pm

Re: Norway is consdiering cancelling troublesome order ...

Tue Nov 13, 2018 6:10 pm

She’s almost entirely under water now. I guess she’s a complete loss. Now the big question is do they build a replacement or just make do?

Image
 
mxaxai
Posts: 3926
Joined: Sat Jun 18, 2016 7:29 am

Re: Norway is consdiering cancelling troublesome order ...

Tue Nov 13, 2018 7:03 pm

Kiwirob wrote:
She’s almost entirely under water now. I guess she’s a complete loss.

Do you know if she had any helicopters on board? They'd be pretty much lost too, now.
 
VSMUT
Posts: 5496
Joined: Mon Aug 08, 2016 11:40 am

Re: Norway is consdiering cancelling troublesome order ...

Tue Nov 13, 2018 7:05 pm

Kiwirob wrote:
Now the big question is do they build a replacement or just make do?


Can they even afford a replacement?

Who is online

Users browsing this forum: No registered users and 23 guests

Popular Searches On Airliners.net

Top Photos of Last:   24 Hours  •  48 Hours  •  7 Days  •  30 Days  •  180 Days  •  365 Days  •  All Time

Military Aircraft Every type from fighters to helicopters from air forces around the globe

Classic Airliners Props and jets from the good old days

Flight Decks Views from inside the cockpit

Aircraft Cabins Passenger cabin shots showing seat arrangements as well as cargo aircraft interior

Cargo Aircraft Pictures of great freighter aircraft

Government Aircraft Aircraft flying government officials

Helicopters Our large helicopter section. Both military and civil versions

Blimps / Airships Everything from the Goodyear blimp to the Zeppelin

Night Photos Beautiful shots taken while the sun is below the horizon

Accidents Accident, incident and crash related photos

Air to Air Photos taken by airborne photographers of airborne aircraft

Special Paint Schemes Aircraft painted in beautiful and original liveries

Airport Overviews Airport overviews from the air or ground

Tails and Winglets Tail and Winglet closeups with beautiful airline logos